Feature Readiness Framework

A practical check of whether a feature has enough documented detail to produce useful placeholder, interim refined, and final user stories.

Portfolio-safe reconstruction. This shows the method without internal feature plans, team structures, or proprietary behavior.

Problem

“Percent of design complete” can hide missing UI interaction rules and system behavior. When that detail is absent, Scrum team refinement becomes feature discovery instead of a focused review of stories.

What I Designed

A feature readiness check tied to the next story-writing stage. It identifies the UI design, UI interaction rules, system behavior specifications, and decisions needed before stories are handed to the team.

Artifact

A three-stage evidence matrix with a clear story output and readiness decision at each stage.

Why It Matters

It directs unresolved feature questions to targeted discovery before Scrum refinement, while giving the team stories with the fidelity needed for planning, refinement, or sprint work.

Artifact / Feature-to-story readiness matrix

Enough detail for the next story stage

Readiness is assessed against the next use of the story. The evidence grows from a coherent feature outline to confirmed behavior that a developer and tester can act on.

Story stage and useFeature evidence neededConsumable story output
1. Placeholder
PI planning
Feature goal and boundary; main actor and lifecycle; conceptual UI journey; major system touchpoints and known dependencies. Open rules and design questions are explicitly named.Stories identify outcomes and likely splits at a planning level. They support sequencing and capacity discussion without implying that detailed behavior is settled.
2. Interim refined
Ready for Scrum team refinement
Preliminary UI design for the relevant flows; documented actions, field behavior, validation, feedback, and recovery; system states, permissions, responses, and cross-flow effects. Material gaps have decision owners and a path to resolution.Stories contain enough scenario and rule detail for the team to refine scope, challenge assumptions, estimate, and identify remaining work. Refinement does not have to invent the feature.
3. Final
Ready for sprint development
UI design and interaction rules are resolved for the story slice; system behavior specifications cover expected, negative, and edge paths; dependencies and required decisions are confirmed.Stories define the behavior and acceptance criteria precisely enough for development and QA to implement and test in a sprint.

Readiness decision

For each required item, record documented, open with an owner, or unknown. A gap that blocks the next story stage becomes a focused feature discovery or decision task before that handoff. The framework measures usable fidelity for a specific purpose, not a percentage of completed design.